PROJECT STATUS
Section 3, Phase 1: Completed May/June 2024
Section 3, Phase 2: Completed May/June 2024
Section 1, Phase 1: Completed Sept 2024
Section 1, Phase 2: Completed Sept 2024
Section 2, Phase 1: Scheduled for Q1 2025
Section 2, Phase 2: Scheduled for Q1 2025
SECTION 3 TOTAL ACTUAL COST: $ 141,201.00
SECTION 1 TOTAL ACTUAL COST: $ 116,075.25
SECTION 2 TOTAL ESTIMATED COST: $ 158,971.06
TOTAL ACTUAL PROJECT COST : $ 257,276.25
TOTAL ESTIMATED PROJECT COST OVERALL : $ 416,247.31
Last updated 01/13/2025
If you see mention of "Quad", it is in fact "Section" since there are three sections broken out between the community. "Quad" was a term used by the contractor who is installing the new mailboxes.
SECTION 2 PHASE 1 KEYS ARE AVAILABLE AT THE CLUBHOUSE
DaysDays
HrsHours
MinsMinutes
SecsSeconds
All Section 1 Phase 1 keys are available for pickup at the Clubhouse.
Photo ID is required.
SECTION 2 PHASE 2 KEYS ARE AVAILABLE AT THE CLUBHOUSE
DaysDays
HrsHours
MinsMinutes
SecsSeconds
All Section 1 Phase 2 keys are available for pickup at the Clubhouse.
Photo ID is required.
SECTION 1 PHASE 1 & 2 PROJECT FILES CAN BE FOUND HERE
Previous Section 3 files have been archived and are available upon request. Please email StonelakeElkGrove@gmail.com
This website and its content is a ongoing work in progress with suggestions highly encouraged. This website is NOT run by FirstService Residential, its staff or the Board of Directors, including any subsequent committee under the Stonelake Master Association. All content of this website has been published by a sole individual acting as a homeowner and not within any capacity the individual holds within the community, with efforts of increased transparency and easier access of what has been made public to the community.
THIS WEBSITE DOES NOT COLLECT ANY ASSOCIATION DUES AND/OR WILL NEVER ASK YOU FOR MONEY.
Copyright © 2024 | Stonelake Elk Grove | All Rights Reserved.